TY - GEN
T1 - A Forensic Evaluation of Projects in Afghanistan Using the Project Definition Rating Index (PDRI)
AU - Mohammady, Sefatullah
AU - Gibson, G. Edward
N1 - Funding Information: After the collapse of the Taliban regime in Afghanistan in the early 2000s, there was a sense of urgency by the United States (U.S.)-led coalition troops to rebuild the Afghan National Security Forces (ANSF). One of the necessities was building military facilities for ANSF throughout the country. Those projects were funded by the U.S. Government, with budget spending going through the U.S Army Corps of Engineers (USACE). Publisher Copyright: © 2020 American Society of Civil Engineers. Copyright: Copyright 2020 Elsevier B.V., All rights reserved.
PY - 2020
Y1 - 2020
N2 - This paper describes a research investigation that retroactively examined front end planning (FEP) by studying fifteen completed military facilities, building projects constructed for the Afghanistan National Security Forces (ANSF) in Afghanistan by the United States Army Corps of Engineers (USACE); these projects represented expenditures of approximately 180 M and were contracted between 2009 to 2015. The investigation collected and analyzed performance information for the projects using a survey questionnaire, follow-up interviews, and a thorough review of the contract documents that established project scope. The study showed that no project was completed on schedule, with changes ranging from +11 percent to +176 percent, averaging 67 percent delay versus original schedule. Cost performance for the projects ranged between 0 to +37 percent with an average cost increase of 12 percent. Results showed that 67 percent of projects reported scope changes, 47 percent encountered differing site conditions, and 40 percent of projects had security issues among others. A forensic PDRI (project definition rating index) evaluation was also performed on the worst performing projects to investigate if the identified problems could have been addressed in front end planning (FEP) for similar types of projects in similar scenarios. In retrospect, many of these problems, such as lack of geotechnical and site investigations, security issues, long lead procurement, labor issues, and so forth could have been addressed through mitigation action during FEP as mapped using the PDRI. At a minimum, contingency could have been set aside to handle unknowns.
AB - This paper describes a research investigation that retroactively examined front end planning (FEP) by studying fifteen completed military facilities, building projects constructed for the Afghanistan National Security Forces (ANSF) in Afghanistan by the United States Army Corps of Engineers (USACE); these projects represented expenditures of approximately 180 M and were contracted between 2009 to 2015. The investigation collected and analyzed performance information for the projects using a survey questionnaire, follow-up interviews, and a thorough review of the contract documents that established project scope. The study showed that no project was completed on schedule, with changes ranging from +11 percent to +176 percent, averaging 67 percent delay versus original schedule. Cost performance for the projects ranged between 0 to +37 percent with an average cost increase of 12 percent. Results showed that 67 percent of projects reported scope changes, 47 percent encountered differing site conditions, and 40 percent of projects had security issues among others. A forensic PDRI (project definition rating index) evaluation was also performed on the worst performing projects to investigate if the identified problems could have been addressed in front end planning (FEP) for similar types of projects in similar scenarios. In retrospect, many of these problems, such as lack of geotechnical and site investigations, security issues, long lead procurement, labor issues, and so forth could have been addressed through mitigation action during FEP as mapped using the PDRI. At a minimum, contingency could have been set aside to handle unknowns.
UR - http://www.scopus.com/inward/record.url?scp=85096786376&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85096786376&partnerID=8YFLogxK
M3 - Conference contribution
T3 - Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020
SP - 181
EP - 190
BT - Construction Research Congress 2020
A2 - Grau, David
A2 - Tang, Pingbo
A2 - El Asmar, Mounir
PB - American Society of Civil Engineers (ASCE)
T2 - Construction Research Congress 2020: Project Management Controls, Materials, Contracts
Y2 - 8 March 2020 through 10 March 2020
ER -