title = "Earned Value Management System (EVMS) Reliability: A Review of Existing EVMS Literature",
abstract = "Supporting project management decisions using an earned value management system (EVMS) brought significant benefits to control schedule and cost for government owners and contractors. However, the lack of a holistic approach in developing and applying an EVMS that is strongly tied to established guidelines tends to cause confusion. This study analyzes existing EVMS studies and suggests management considerations for successful EVMS implementation. Based on a review of literature, this paper identifies a need for improving the reliability of EVMS. Technical guidelines assist in the application of EVM good practices, which can lead to a reliable EVMS. Moreover, the literature review emphasizes that a parallel assessment considering non-technical elements such as the organizations' management culture, is essential to improve reliability.",
keywords = "EVMS environment, Earned value management system, Integrated project management, Maturity, System reliability",
author = "Namho Cho and {El Asmar}, Mounir and Gibson, {G. Edward} and Vartenie Aramali",
note = "Funding Information: This study was funded by the U.S. Department of Energy. The authors would like to thank the research team members of this study entitled: “Improving the Reliability of EVMS Compliance Reviews and EVMS Maturity Level Assessments.” Publisher Copyright: {\textcopyright} 2020 American Society of Civil Engineers.; Construction Research Congress 2020: Project Management Controls, Materials, Contracts ; Conference date: 08-03-2020 Through 10-03-2020",
year = "2020",
language = "English (US)",
series = "Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020",
publisher = "American Society of Civil Engineers (ASCE)",
pages = "631--639",
editor = "David Grau and Pingbo Tang and {El Asmar}, Mounir",
booktitle = "Construction Research Congress 2020",
}