TY - JOUR
T1 - Novel Earned Value Management System Maturity Framework and Its Relation to Project Performance
AU - Aramali, Vartenie
AU - Gibson, G. Edward
AU - El Asmar, Mounir
AU - Sanboskani, Hala
N1 - Publisher Copyright: © 2023 This work is made available under the terms of the Creative Commons Attribution 4.0 International license.
PY - 2023/6/1
Y1 - 2023/6/1
N2 - Earned value management systems (EVMS) are used by industry practitioners to successfully manage projects and programs; however, there has been no past study to characterize and evaluate the impact of EVMS maturity on project performance. This paper introduces a novel framework, developed to measure the EVMS maturity, composed of 56 attributes arrayed across ten subprocesses, which together make up an integrated project/program management system. This paper describes how the framework was conceived and developed, based on literature review and data collected from industry workshops. Then, it examines the relationship between EVMS maturity and ten project performance metrics through statistical analyses. The study analyzed project data from 35 projects and programs worth over $21.8 billion in total cost. For this sample, results showed statistically significant differences between projects with high and low EVMS maturity; on average, projects exhibiting high EVMS maturity have 54% less cost overruns and 19% less change orders versus their performance measurement baseline. Higher maturity projects and programs also achieve better customer satisfaction, meet business objectives more often, and are more often in compliance with EVMS standards and guidelines. This paper contributes to the body of knowledge by providing a practical and novel framework for assessing the maturity of earned value management systems. Practitioners can use the framework to improve their integrated project and program management.
AB - Earned value management systems (EVMS) are used by industry practitioners to successfully manage projects and programs; however, there has been no past study to characterize and evaluate the impact of EVMS maturity on project performance. This paper introduces a novel framework, developed to measure the EVMS maturity, composed of 56 attributes arrayed across ten subprocesses, which together make up an integrated project/program management system. This paper describes how the framework was conceived and developed, based on literature review and data collected from industry workshops. Then, it examines the relationship between EVMS maturity and ten project performance metrics through statistical analyses. The study analyzed project data from 35 projects and programs worth over $21.8 billion in total cost. For this sample, results showed statistically significant differences between projects with high and low EVMS maturity; on average, projects exhibiting high EVMS maturity have 54% less cost overruns and 19% less change orders versus their performance measurement baseline. Higher maturity projects and programs also achieve better customer satisfaction, meet business objectives more often, and are more often in compliance with EVMS standards and guidelines. This paper contributes to the body of knowledge by providing a practical and novel framework for assessing the maturity of earned value management systems. Practitioners can use the framework to improve their integrated project and program management.
UR - http://www.scopus.com/inward/record.url?scp=85151310961&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85151310961&partnerID=8YFLogxK
U2 - 10.1061/JCEMD4.COENG-12985
DO - 10.1061/JCEMD4.COENG-12985
M3 - Article
SN - 0733-9364
VL - 149
JO - Journal of Construction Engineering and Management
JF - Journal of Construction Engineering and Management
IS - 6
M1 - 04023031
ER -